|
R. GOVIND - M.H. YILMAZ, 2017; ICBEST 2017 Facade Failures, Seminar Article
FAÇADE FAILURES DUE TO PROJECT DESIGN DEVELOPMENT AND WORKMANSHIP
Abstract
There has been and will always be failures in construction business, like any other business. Engineers and Consultants are paying serious attention to prevent and learn from them.
There is nothing stationery against the nature forces. It is quite often in the façade industry, either designers pay less or no attention to the building movements or underestimate its interactions. In the building envelope, the impact will be so severe with devastating damages to the building and its services; resulting expensive rectifications and disruptive occupancy of the building.
Mistakes are being made during the design, fabrication and installation stages. However most of them are still caused by, misinterpreting the basic physics rules and the main principles.
Every failure tells us something, only if we listen to it correctly. We must not only criticize, punish or just fix it, but learn from them. We need to empathize to see which mistakes are repeated, which main principal is not understood by the designers and installers.
Basic design principles of joints and allowances for adequate movements start from these typical facade details. Simple verifications and design process may avoid disruptive impact on post completions.
Not only avoiding failures, but also using the information, researching and collecting data, will help us improve the Facade sector.
On this note two cooperating Facade Consultant Companies, each working in different regions and experienced in dealing with problematic issues, came together to share the experiences by presenting a detailed work, on reasons, facts, statistics, solutions, suggestions and future preventions on Facade Failures.
Keywords
Façade Failures, Curtain Wall damages, Cladding Failures, …
1. Introduction
Buildings as homes, offices, hotels or
hospitals, are man-made structures intended for human use. These are shelters
and physical divisions of the human habitat which supply comfort and safety.
Many of the definitions of Building say “a structure with a roof and wall for
people use”. Wall is something mentioned primarily and we believe it refers to
the outer walls.
Outer walls of the building, together with the windows,
glazings and claddings, are either a border or a filter between the indoor and
outdoor conditions. These are the elements that provide most of the comfort
conditions we need.
The severity of the problem, with the building envelope, may
vary from a minor performance loss to a devastating collapse, but in either case
our comfort or more critically our safety will be under threat. Therefore this
means, the purpose and functionality of this element of the building is not
succeeded.
There are and have been many problems occurred with the windows, curtain walls
and claddings (envelope) of the buildings. And mainly we have learned from them
a lot. But the technology has developed very fast. The Investments are getting
larger every decade, also the size of the buildings and complexity.
Unfortunately the speed of learning from past mistakes is not enough to keep up
following.
It is not possible to overview all mistakes and not necessary to
examine the ones that are not repeating. In this study, we will consider some of
these failures and mistakes through our 50 years old experience and daily facts
from some cases.
Many of these failures due to miscalculations or poor
engineering are studied before. Furthermore there are more complex problems such
as ‘nickel-sulfide inclusion’, which causes serious concerns on glass
applications. Here we will mainly focus on the mistakes or misses that were made
during the designs, shop drawing preparation or design development and
implementation stages including workmanship issues and construction failures.
That we believe, these could have been easily prevented with right approach and
checks in place. And we will try to find what reality lies behind these
mistakes, we will try to go to the roots and find if there is a common solution.
2. Methodology
The authors of this paper are from Turkey and India, consultants of projects mainly in Turkey, Singapore, Malaysia, Russia, India, North Africa and middle east countries. There are of course some similarities and differences of the failures. We are going to show some case studies, and some other examples. These are some mistakes that we observed in different projects. We have used examples from different projects in each single case study. So we can tell that these are common mistakes or common problems.
Failures must be sorted in types. Miscalculation and poor engineering problems, materials and supply chain problems, design problems and workmanship problems are the most important ones. We will focus on the last two.
2.1 Case Study 1
In fact the first case study is not only one case, this is one common
problem from three different actual projects of FMT Façade Consultants. The same
mistake has been done by the designers during the shopdrawing phase and also by
the technicians during the installation.
Let’s have a look at some design development stage problems;
The first project is in Istanbul, erected recently (year 2014). Below
drawing was submitted by the façade contractor as the shopdrawing. The Façade of
this part of this building has been designed as “window wall”, glazed facades
are located between slabs and the slab edges are covered with metal sheet
cladding. Therefore in each floor there is a bottom end of the glazed façade.
Because of the heights of the floors and since in Turkey there is not any
developed window wall systems such as in the U.S., usually the façade specialist
are using Stick Curtain wall system elements.
Figure 1, submitted detail of Istanbul1 Project
This is a Stick Curtain wall system, used as
window wall, and the façade contractor submitted this drawing for the bottom
connections. Façade Consultant was involved in the project after installation
started, to inspect the problems in this project.
As it can be seen, there is an insulation
membrane shown with red. And the technicians in the jobsite applied the
membranes exactly as they are in the drawings.
Figure 2, the work on the site
As shown in the above picture, technicians kept respecting the shopdrawings. And
as it can be seen in the picture, the water insulation is in front of the system
elements.
Below drawing was an explanatory warning to the
Contractor.
Figure 3, graph shows misplacement of membrane
And also
water drainage pipes were not used. The result is shown in the pictures below.
Figure 4, water leakage
These leakages were experienced after the main contractor was warned with the
report including figure 3 above. Finally the façade specialist, used drainage
fittings (pipes) and sealed the bottom line of the system in order to direct the
water out.
Figure 5, water drainage fitting
This case shows us that neither the white collar people preparing these drawings
nor the blue collars, have any idea about the façade system, how the water
moves, how the pressure difference helps water infiltration and what
condensation is.
These are all basic
principles that can only be learned through the scientific approach. And must be
taught to all façade teams including the installation technicians.
Another design mistake with the same problem;
Figure 6, Submitted Detail from Moscow Project
But this case is
from another city, another Country and by another Façade specialist. The Russian
contractors did the same mistake in their shopdrawings.
Fortunately, Façade consultant was involved during the design development stage
so the contractor was warned and they corrected these details for allowing the
water drains outside.
In these two
examples the problem was caused by the shopdrawing designer, but below example
shows us even though the drawing was correct, the installation crew made the
same mistake;
Figure 7, Installation of
Istanbul2 Project
2.2 Case
study 2
Below example is from
India.
As we have mentioned, there
is nothing stationery against the nature forces. It is quite often in the facade
designs industry, either designers pay no attention to the building movements or
underestimate its interactions.
The
impact will be so severe in the building envelope with devastating damages to
the building and its services. There will be expensive rectifications and
disruptive occupancy of the building as a consequence. Some facts of similar
instances from a building investigation have been presented here.
Figure 8, Building (in Mumbai) with shattered glass units
Figure 9, Quick Facts; Key figures of glass breakages of the building
Following; showing pattern of failure modes of Unitized Curtain Wall systems and
causes
Figure 10, Failure modes
Pictures illustrate the impact
and post instance scenario of façade glazing panels behaviors. Excessive joints
movements are evident in these pictures of external and internal façades
Figure 11, External view of joints failures
Building Facades – Movements and joint designs;
Basic design principles
of joints and allowances for adequate movements start from these typical facade
details.
Simple verifications and design process may avoid disruptive impact on post
completions.
Figure 12, Joint design illustration
2.3 Case study 3
Below there are some pictures from a very common mistake about the thermal
movement ignorance. Either the designers or the installation crew,
underestimated the thermal expansions.
These examples are from
Istanbul and Moscow.
Figure 13, Spacer Left in the expansion Joint
Figure 14, Temporary Adjustment Screw Left in the expansion Joint
Figures 15&16, Expansion not allowed with fixed bolts.
It
is clearly seen that, in these four different jobsites, the façade specialist
installation crew have no idea about the thermal expansions and thermal
expansion joints.
Therefore these cases are showing us the
importance of the scientific facts and how easily these facts are underestimated
due to the lack of knowledge and education.
3. Results and Discussion
Failures are threats to human life and safety,
moreover failures cause loss of time, money, prestige and most importantly
precious human life.
What we have seen in these case studies
could have been prevented easily if the designers or implementing team had
specific skills and experiences. On the other hand it is very obvious that,
overall skills and manpower of some building envelope industry and supply chain
are trained and already upgrading their skills as well as the adequate checks
and supervisions are completed.
For example, the system designs
of well known system house companies are tested and verified or IGU’s that are
obtained from producers are under well QAQC procedures. But when it comes to the
construction phase and the time is one of the most important issues, then the
controls and verifications are getting weaker.
System houses
design the systems and their components very well and describe it in their
manuals sufficiently, but when it comes to connect them with other structures,
mount to the building structures, both the design developers of the
construction, the crew preparing the shopdrawings, and the foremen plus workers
skip some crucial basics of physics and general rules.
Pressure
differences – pressure equalization, building movements, pressure gradients of
the facades, thermal movements are the most important examples of these rules.
It seems that those technical teams do not have enough education about the basic
physics rules. Of course we are speaking about our regions but let us not forget
that these are the fastest growing regions and the demand of buildings is still
increasing.
It is very clear that the project detail designers
and the installation crews must be educated about the building physics, they
need to know why there is a thermal expansion gap or what is water drainage.
The façade specialist companies must give importance to their inspections as
well as their internal educations. I have seen some internal random inspections
of façade specialist companies but only in few cases. Usually there is no double
check with the stage of design development – shopdrawings and installation. On
the contrary it is observed that the controls during the factory productions are
sufficient enough. Therefore the façade specialist must give the same importance
to the jobsites as well as their factories.
Another safe way of
controlling the jobsite phase must be done by the developers or main contractor
by using the façade consultants.
Designer’s Skills vs Practice
Matrix illustrates the relationship between the
designer’s skills and possible outcome of the designs.
Figure 17, Skills
Figure 18, Rating Design
Either during the designing stage or the site works, the power of nature and
materials must not be underestimated, on the contrary these must be calculated
very carefully. Even though the correct application is shown in the drawings,
the installer can underestimate and continue with his own way. This implicates
that the education of both the designers and the installers, has a very high
importance and necessity.
References
Yilmaz, H. (1999). Cephe Sistemleri ve Cephe Kaplamaları, YEM Yayınları.
TS EN ISO 13830: Curtain Wall Product Standard, 2016.
ICBEST Istanbul, 15-18 May 2017, Istanbul / Turkey
|
|